78th Avenue East / 192nd Street East (CRP 5641)

78th Avenue East / 192nd Street East
CivicSend Slideshow Left Arrow Slideshow Right Arrow
CivicSend Slideshow Left Arrow Slideshow Right Arrow
CivicSend Slideshow Left Arrow Slideshow Right Arrow
What's Happening
 
Engineering: We’re completing engineering for a project (CRP 5641) to be constructed at some time in the future.

About the Project

Planned improvements to the intersection of 78th Avenue East / 192nd Street East (CRP 5641) are intended to increase the efficiency of the intersection and improve safety. Improvements would include the following:
  • Reconstructing the existing traffic signal system
  • Installing street lighting at the intersection
  • Constructing left-turn lanes on 78th Avenue East
  • Constructing cement concrete curb, gutter, and sidewalk on 78th Avenue East
  • Reconstruction of the storm drainage system
Design work on the project will stop once enough detail has been generated to enable preparation of right-of-way plans. No additional work, such as right-of-way acquisition or construction for the project is anticipated in the foreseeable future.

Project Timeline


March 2014 to March 2017:
Preliminary engineering, environmental review, preliminary plans, and estimate.

March 2017 and beyond: Right-of-way acquisition, environmental permitting, final engineering, and construction are all dependent on additional funding. The schedule for these activities has not been determined.

Contact Us
Send a message arrow
Patrick Baughman, P.E., PMP
Design Supervisor
Phone: (253) 798-3157
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409