72nd Street East (270 Feet West of Bentley Road) (CRP 5845)

5845ProjectHeaderPhoto.JPG
Location pin
Camera
Rolled up paper icon

What's Happening

Engineering: This project is in the preliminary stages of engineering.

Land: Right of Way and/or Temporary Easement needs will be evaluated.

Survey:
A topographic survey has been performed.

Environmental:
Necessary environmental permits will be obtained.

Geotechnical: A geotechnical study will be performed.

About the Project


Planned improvements to 72nd Street East - 270 ft w/o Bentley Road (CRP 5845) are intended to repair the slide that occurred along the north side of 72nd Street East in December of 2015.

Project Timeline


Fall 2016: Begin preliminary design.

Spring 2017: Right of Way/Easement acquisition

2018: Construction.