Foothills Trail (South Prairie to Buckley) - Phase 3

Foothills Trail (South Prairie to Buckley) - Phase 3

What's Happening


Pierce County issued the Notice to Proceed on June 19, 2017. The Contractor, Pivetta Brothers Construction, will be on site performing the following work:
  • Installing erosion control measures
  • Clearing and grubbing
  • Excavation and embankment for the new trail

About

 the Project

 


Planned improvements to Foothills Trail (South Prairie to Buckley) - Phase 3 (Program No. 6164) will tie the previously built section from Orting to South Prairie to the Phase 1 section of trail.  Improvements will include the following:
  • Adding 1 mile of new trail, including an elevated pin pile bridge and a horse path adjacent to the trail.

Project Timeline

April 07, 2017: Bid Opening

April 17, 2017: Pierce County awarded the project to Pivetta Brothers Construction, Inc.

May 03, 2017: Pierce County hosted the Pre-Construction Meeting

June 19, 2017: Pierce County issued the Notice to Proceed

Oct 2017: Anticipated Substantial Completion

Nov 2017: Anticipated Physical Completion


Contact Us
Send a message arrow
Henry Gertje, P.E.
Construction Supervisor
Phone: (253) 798-6826
Pivetta Brothers Construction, Inc.
Contractor
Phone: (253) 862-7290
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
1812 Pease Avenue
Sumner, WA 98390