Foothills Trail - Buckley Pavement Rehabilitation (P-110485)

​What's Happening

Pierce County issued the Notice to Proceed for October 2, 2017. The Contractor, Miles Resources, will be on site performing the following work:
  • Installing erosion control measures
  • Closing the trail for 20 Working Days
  • Excavating the trail section
  • Embanking and installing root barriers
  • Paving

About the Project


The contract for Foothills Trail - Buckley Pavement Rehabilitation (P-110485) provides for the construction of approximately 2,784 linear feet of asphalt concrete rehabilitation for Foothills Trail, beginning at the Buckley City Limits on SR-165 and extending south.

​Project Timeline


September 1, 2017: Bid Opening held

September 12, 2017: Pierce County awarded the contract to Miles Resources

September 27, 2017: Pierce County hosted the Pre-construction Meeting

October 2, 2017: Pierce County issued the Notice to Proceed

Fall 2018: Anticipated Substantial Completion

Fall 2018: Anticipated Physical Completion
Contact Us
Send a message arrow
Henry Gertje, P.E.
Construction Supervisor
Phone: (253) 798-6826
Miles Resources
Contractor
Phone: (253) 383-3585
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
400 Valley Avenue NE
Puyallup, WA 98372