ADA Improvement Program - 2019

What's Happening

Engineering: We're beginning the preliminary engineering for the project. We'll be completing the field survey of the existing and proposed ADA ramp locations. 

About the Project

Planned improvements for the ADA Improvement Program - 2019 (CRP 5881) are intended to improve ADA accessibility and sidewalk connectivity in the vicinity of 177th Street East and 180th Street East west of 38th Avenue East and will include the following:

  • Removing and reconstructing existing ADA ramps within the project area.
  • Adding new ADA ramps within the project area.

Project Timeline

March 2018 to May 2018: Complete field surveys.

May 2018 to December 2018: Complete preliminary engineering and environmental documentation. 

January 2019 to March 2019: Complete construction plans, specifications, and estimates.

Summer 2019: Construct Improvements.