22nd Avenue East / 152nd Street East (CRP 5650)
78th Avenue East and 184th Street East

Project Location
Project Location
Project Photos
Project Photos
Roadway Section
Finished Intersection

What's Happening
Engineering: Finalizing the preliminary engineering phase that will provide final Right-Of-Way plans and 75% complete on construction plans.

Land: Right-Of-Way acquisitions will begin once Right-of-Way plans are complete.
About the Project
Planned improvements to the intersection of 22nd Avenue East and 152nd Street East (CRP 5650) are intended to increase the efficiency of the intersection and improve safety. The improvements would include the following:
  • Adding a westbound left-turn lane and an eastbound right-turn lane on 152nd Street East.
  • Adding a right-turn lane on northbound 22nd Avenue East.
  • Installing concrete curb, gutter, and sidewalk.
  • Installing an enclosed storm drainage system, and water quality treatment and storage facilities.
  • Installing a traffic signal system.
  • Improving intersection street lighting.
Project Timeline
April 2016 to April 2017: Complete preliminary engineering phase.

May 2017 to October 2018: Begin final engineering phase of which includes environmental documentation, acquire Right-Of-Way, complete construction plans, specifications, and estimates.

November 2018:  Advertise project for bids