94th Ave E - 850' S/O 144th St E to 300' S/O 136th St E (CRP 5533)
94th Ave E


Project Location

Project Photo

Roadway Section

What's Happening
Engineering: We're beginning the preliminary engineering for the project. Currently we've completed the field survey of the corridor, and are refining the vertical roadway alignment.
About the Project
Planned improvements to 94th Avenue East from approximately 850 feet south of 144th Street East to 300 feet south of 136th Street East (CRP 5533) are intended to increase capacity and relieve traffic congestion, and include the following:
  • Expanding to five lanes with a two-way left-turn lane.
  • Adding concrete curbs, gutters and sidewalks.                              
  • Adding street lighting.
  • Adding a new permanent traffic signal at the 94th Avenue East / 144th Street East intersection.
  • Adding an enclosed storm drain system, as well as stormwater treatment facilities.
Project Timeline
February 2014 to December 2016: Complete preliminary engineering and right-of-way plans.

December 2016 and Beyond: Right-of-way acquisition, environmental documentation, construction plans, specifications, estimates, and construction.  These activities are all dependent on additional funding.
Contact Us

Patrick Baughman, P.E., PMP
Design Supervisor
Ph: (253) 798-3157
Contact Us

Public Works
Tacoma Mall Office Bldg
4301 South Pine Street
Suite 628
Tacoma, WA 98409-7207
Ph: (253) 798-7250