Go To Search
Click to Home
Find a Department
78th Avenue East / 192nd Street East (CRP 5641)
78th Ave E and 192nd St E


Project Location

Project Photo

Finished Intersection

What's Happening
Engineering: We’re completing engineering for a project (CRP 5641) to be constructed at some time in the future.

About the Project
Planned improvements to the intersection of 78th Avenue East / 192nd Street East (CRP 5641) are intended to increase the efficiency of the intersection and improve safety.  Improvements would include the following:
  • Reconstructing the existing traffic signal system
  • Installing street lighting at the intersection
  • Constructing left-turn lanes on 78th Avenue East
  • Constructing cement concrete curb, gutter, and sidewalk on 78th Avenue East
  • Reconstruction of the storm drainage system

Design work on the project will stop once enough detail has been generated to enable preparation of right-of-way plans.  No additional work, such as right-of-way acquisition or construction for the project is anticipated in the foreseeable future.
Project Timeline
March 2014 to October 2016: Preliminary engineering, environmental review, preliminary plans, and estimate.

October 2016 and beyond: Right-of-way acquisition, environmental permitting, final engineering, and construction are all dependent on additional funding. The schedule for these activities has not been determined.
Contact Us

Patrick Baughman, P.E., PMP
Design Supervisor
Ph: (253) 798-3157
Contact Us

Public Works
Tacoma Mall Office Bldg
4301 South Pine Street
Suite 628
Tacoma, WA 98409-7207
Ph: (253) 798-7250