136th St E - 160' w/o 98th Ave Ct E to 450' w/o SR-161 (CRP 5813)
136th St E - wo 98th Ave Ct E to wo SR 161



Project
Location

Project
Photo

Contract
Specs


Contract
Plans

Bid
Tabs

What's Happening
Pierce County issued the Notice to Proceed on June 27, 2016. The contractor, Reed Trucking, will be on site performing the following work:
  • Constructing concrete curb, gutter, and pervious concrete sidewalk where gravel shoulder currently exists on the north and south sides of 136th Street East in front of Ballou Junior High School.
  • Upgrading the existing roadway lighting to energy efficient LED lighting.
About the Project
Planned improvements to 136th Street East - 160 feet west of 98th Avenue Court East to 450 feet west of SR-161 (CRP 5813) are intended to enhance pedestrian safety and access. The improvements will include the following:
  • Constructing concrete curb, gutter, and pervious concrete sidewalk where gravel shoulder currently exists on the north and south sides of 136th Street East in front of Ballou Junior High School.
  • Upgrade the existing roadway lighting to energy efficient LED lighting.
Project Timeline
May 10, 2016: Pierce County awarded the contract to Reed Trucking

June 8, 2016: Pierce County hosted the Pre-Construction Meeting

June 27, 2016: Pierce County issued the Notice To Proceed

Summer 2016: Anticipated Substantial Completion and Physical Completion dates  
Contact Us

Henry Gertje, P.E.
Construction Supervisor
Ph: (253) 798-6826
Contact Us

Public Works
Tacoma Mall Office Bldg
4301 South Pine Street
Suite 628
Tacoma, WA 98409-7207
Ph: (253) 798-7250

Contractor
Reed Trucking
2207 Inter Avenue, Suite A
Puyallup, WA 98372
Ph: (253) 256-4365