Foothills Trail (South Prairie to Buckley) - Phase 2
Foothills Trail
            
           
Vicinity Map
Project
Location
Photo
Project
Photo
ROW Plan
Right of Way
Plans
 
Specifications
Contract
Specs

Plans
Contract
Plans
Bid Tabs
Bid
Tabs

What's Happening
Pierce County issued the Notice to Proceed for July 13, 2016. The contractor, Pivetta Brothers Construction, is on site performing the following work:
  • Clearing and Grubbing
  • Installing erosion control
  • Preparing for Pin Pile Bridge installation
About the Project

Planned improvements to Foothills Trail - South Prairie to Buckley
(
CSM 6164)
 will tie the previously built section of the trail (Phase 1) to the existing Foothills Trail section in the City of Buckley.  Improvements will include the following:                            

  • Adding 1.32 miles of new trail, including 0.54 miles of elevated pin pile bridge
  • Adding 0.78 miles of horse path adjacent to the trail.


                       
Project Timeline
May 13, 2016: Pierce County awarded the contract to Pivetta Brothers 

June 16, 2016: Pierce County hosted the Pre-Construction Meeting

July 13, 2016: Pierce County issued the Notice To Proceed

Spring 2017: Anticipated Substantial Completion and Physical Completion dates  
Contact Us

Henry Gertje, P.E.
Construction Supervisor
Ph: (253) 798-6826
Contact Us

Public Works
Tacoma Mall Office Bldg
4301 South Pine Street
Suite 628
Tacoma, WA 98409-7207
Ph: (253) 798-7250

Contractor
Pivetta Brothers

1812 Pease Ave
Sumner, WA 98390
Ph: (253) 862-7290
Website