Steilacoom Ferry Landing - Wing Walls and Dolphins
Steilacoom Ferry Landing - Wing Walls and Dolphins


Project Location

Project Photo

What's Happening
Engineering: This project is currently in final design.

Land: All improvements will be within the existing right of way.
About the Project
Planned improvements to the Steilacoom Ferry Landing - Wing Walls and Dolphins (Program No. 6959) will include the following:
  • Removal of the existing idle ferry timber wing walls, timber dolphins, and maintenance access. 
  • Adding 60 feet of concrete trestle, steel wing walls, two new steel dolphins, and a 6 foot wide aluminum pedestrian / maintenance access trestle and transfer span. 
Project Timeline
Spring 2017: Estimated project advertisement 