8th Ave S (SR-702 to 336th St S and 304th St S to 1,050' S/O SR-507)
project header photo



Project
Location

Project
Photo

Contract
Specs


Contract
Plans

Bid
Tabs

What's Happening
Pierce County has issued the Notice to Proceed for June 22, 2016. The Contractor, Miles Resources, is on site preforming the following:
                               
  • Repairing the bridge deck.
About the Project
Planned improvements to 8th Ave S - SR-702 to 336th St S and 
304th St S to 1,050' S/O SR-507 (CRP 5823 & CRP 5824)
 
will include the following:
  • Repairing the existing pavement in areas where needed. 
  • Adding a two-inch overlay to the existing roadway. 
  • Bridge deck repair.
  • Removing and resetting guardrail.
Project Timeline
May 10, 2016: Pierce County awarded the contract to Miles Resources

May 31, 2016: Pierce County hosted the Pre-Construction Meeting

June 22, 2016: Pierce County issued the Notice To Proceed

Summer 2016: Anticipated Substantial Completion and Physical Completion dates  
Contact Us

Henry Gertje, P.E.
Construction Supervisor
Ph: (253) 798-6826
Contact Us

Public Works
4301 South Pine Street,
Suite 628
Tacoma, WA 98409
Contractor
Miles Resources LLC
400 Valley Avenue NE
Puyallup, WA 98372
Ph: (253) 838-9090
Website