Engineering: We are completing the preliminary engineering phase for the project. Currently we are focusing on the design of the drainage systems as well as other miscellaneous project details.

Land: The preliminary Right-of-Way plans are being worked on.

Geotechnical: A consultant to perform geotechnical studies will be selected to provide information regarding the project pavement, stormwater facilities, retaining walls, and signal systems.
About the Project
Planned improvements to both sides of the 62nd Avenue Northwest / 144th Street Northwest (CRP 5801) are intended to improve safety and traffic operations.  Improvements will include the following:
  • Install a traffic signal system
  • Adding a westbound left-turn lane
  • Adding stormwater treatment and storage facilities
Project Timeline
Sept 2016: Complete preliminary engineering, construction cost estimate, and preliminary Right-of-Way plans. 

Oct 2016 to Sept 2017: Right-of-Way acquisition, final engineering.

Oct 2017: Start utility relocations, construction.