Sunrise Parkway East / 122nd Avenue East (CRP 5786)
Sunrise Pkwy E and 122nd Ave E


Project Location

Project Photo

Finished Intersection

What's Happening
Engineering: The project is in the early stages of the preliminary engineering phase. Finalizing the roadway layout, and beginning the storm drainage design. Beginning the environmental geotechnical studies.
About the Project
Planned improvements to the intersection of Sunrise Parkway East / 122nd Avenue East (CRP 5786) are intended to increase efficiency of the intersection and improve safety.  Improvements will include the following:
  • Adding two southbound left-turn lanes.
  • Adding a northbournd left-turn lane.
  • Install cement concrete curb, gutter, and sidewalks.
  • Install an enclosed storm drainage system, and water quality treatment and storage facilities. 
  • Install street lighting.
  • Install a new traffic signal system.
Project Timeline
May 2016 to May 2017: Topographic survey work of the existing conditions, produce preliminary construction plans, prepare a cost estimate, and finalize right-of-way plans, and complete the Preliminary Engineering Phase.

June 2017 to 2020: Right-of-Way acquisition, environmental permitting, final engineering, and construction of the intersection pending funding availability.
Contact Us

Gregory Hess, P.E.
Design Supervisor
Ph: (253) 798-2283
Contact Us

Public Works
Tacoma Mall Office Bldg
4301 South Pine Street
Suite 628
Tacoma, WA 98409-7207
Ph: (253) 798-7250