Basic Project Information
Project Manager Fred Hogan (253) 798-6723 ccb
Location 930 Tacoma Ave. S.
Tacoma, WA 98402 (Directions)
Architect Architects Rasmussen Triebelhorn
Contractor Pease Construction
Completion Date August 2008
The Phase 2 renovations include construction improvements to the second floor North Wing (C-Wing) of the County-City Building and a small portion of work to the North Wing to attach it to the adjacent jail.
  • Complete Remodel of 2nd Floor North Wing
  • Three New Superior Court Courtrooms
  • Superior Court Administration Space
  • Enhanced Courthouse Security Systems
Phase 2 is part of a four phase overal renovation of the County-City Building. The four phases will be the largest remodel of the County-City Building in a decade and involves nearly 60,000 square feet on five floors.
  • Phase 1 Complete remodel of the 3rd and 4th floors
    (Completed June, 2007)
  • Phase 2 Remodel of the second floor north wing
  • Phase 3 Remodel of a portion of the fifth floor central wing
  • Phase 4 Partial remodel of the nineth floor
The County-City Building is home to multiple Pierce County and City of Tacoma departments including Superior, District and Municipal Courts.






















Current Work Includes:

ENTRANCE CLOSURE: The direct route from the Merit Building to the County-City Building will close permanently Friday, Sept. 14 when the breezeway between South 9th Street and the loading dock entrance is shut down for the CCB Phase 2 renovation project. The two entrances to the north wing (C-Wing) from the breezeway also will be closed permanently.

Phase 2 is aimed at converting space on the 2nd floor of C-Wing into three courtrooms and adminstrative space for Superior Court and installing enhanced courthouse security systems. A new entry will be provided at the north end of C-wing as part of the $8.9 million Phase 2 work.
The interior stairwell at the north end of C-Wing will be temporarily closed on and off the 2nd Floor. The north stairwell will serve as an emergency exit to the first-floor and Tacoma Avenue for the duration of the project. View Map
Click on map to enlarge.

Back to Top



Meeting Date Minutes/Handouts
Wednesday, August 8, 2007 Minutes
Tuesday, September 11, 2007 Minutes
Tuesday, September 25, 2007 Minutes
Tuesday, October 2, 2007 Minutes
Tuesday, October 9, 2007 Minutes
Tuesday, October 16, 2007 Minutes
Tuesday, October 23, 2007 Minutes
Tuesday, November 6, 2007 Minutes
Tuesday, November 13, 2007 Minutes
Tuesday, December 4, 2007 Minutes
Tuesday, December 11, 2007 Minutes
Tuesday, January 8, 2008 Minutes
Tuesday, January 15, 2008 Minutes
Tuesday, January 22, 2008 Minutes


August24 8-24-07 Predemolition

Sept 9-11-07 Demolition

Sept19 9-19-07 Demolition

Sept 09-20-07 Demolition

Sept 09-28-07 Demolition


September 2007. Demolition & Abatement of 2nd Floor C-Wing of County-City Building.
Oct 10-15-07 Demolition

Oct 10-17-07 Demolition

Oct 10-18-07 Demolition

October 2007. Topping slab demolition & install 1st floor plumbing and electrical above ceiling
Nov 11-01-07 Demolition

Nov 11-19-07 Demolition

November 2007. Install concrete slabs & waterproofing and install exterior walkway steel support
Dec 12-04-07 Construction

Dec 12-20-07 Construction


December 2007. Demolish walls & ceiling in existing jail sallyport and construct temporary security walls. Install new exterior windows & spandrel panels, ductwork, and frame new walls & security door frames.
Jan
01-3-08 Construction

Jan
01-15-08 Construction


January 2008. Install plumbing, electrical, and security electronics rough-in. Complete installation of exterior walkway at North wall.
Feb
Construction

February 2008. Install concrete ramp and walls at existing jail sallyport. Install electrical wiring and drywall at framed walls.
Mar
Construction

March 2008. Finish, texture drywall, and paint walls. Complete railing installation at ramp in ijail sallyport.
Apr
Construction

April 2008. Install ceiling, courtroom wood paneling, and casework. Install resilient flooring, light fixtures, and plumbing fixtures.
Monthly
May 2008.
Install fire sprinkler heads, detention fixtures, and electrical devices. Install window treatment, carpet flooring, and doors & hardware.
Monthly
June 2008.
Install decorative metal ceilings, final electrical devices, controls, toilet accessories
Monthly
July 2008.
Install courtroom pews, test fire alarm & security systems and final inspection
Monthly
August 2008.
Final Completion

2011 Performance Report
Project highlights, Facilities Benchmarks


Results of Fall 2011 Tax Title Auction
Auction was held Oct. 7th

Privacy Policy | Text Only Version | Webmaster

Copyright ©1996-2012 Pierce County Washington. All rights reserved. Last Modified Dec 15 2009 2:14PM.