| Basic Project Information |
| Project Manager |
Fred Hogan (253) 798-6723 |
 |
| Location |
930 Tacoma Ave. S. Tacoma, WA 98402 (Directions) |
| Architect |
Architects Rasmussen Triebelhorn |
| Contractor |
Pease Construction |
| Completion Date |
August 2008 |
The Phase 2 renovations include construction improvements to the second floor North Wing (C-Wing) of the County-City Building and a small portion of work to the North Wing to attach it to the adjacent jail.
- Complete Remodel of 2nd Floor North Wing
- Three New Superior Court Courtrooms
- Superior Court Administration Space
- Enhanced Courthouse Security Systems
Phase 2 is part of a four phase overal renovation of the County-City Building. The four phases will be the largest remodel of the County-City Building in a decade and involves nearly 60,000 square feet on five floors.
- Phase 1 Complete remodel of the 3rd and 4th floors
(Completed June, 2007)
- Phase 2 Remodel of the second floor north wing
- Phase 3 Remodel of a portion of the fifth floor central wing
- Phase 4 Partial remodel of the nineth floor
|
| The County-City Building is home to multiple Pierce County and City of Tacoma departments including Superior, District and Municipal Courts. |
| |
 |
|
 |
|
|
|
|
|
Asbestos Remediation Air Monitoring Reports from Dennis Rauschenberg with ORION Environmental
- August 27, 2007
- August 28, 2007
- August 29, 2007
- August 30, 2007
- September 5, 2007
- September 6, 2007
- September 7, 2007
- September 12, 2007
- October 2, 2007
- October 3, 2007
- October 4, 2007
- October 5, 2007
- October 8, 2007
- October 9, 2007
- October 10, 2007
- October 11, 2007
- October 12, 2007
- October 15, 2007
- October 16, 2007
- October 26, 2007
- October 29, 2007
- January 14, 2008
- January 15, 2008
- January 16, 2008
- January 21, 2008
- January 22, 2008
- July 28, 2008
- July 29, 2008
- July 30, 2008
- July 31, 2008
- August 4, 2008
Demolition of 2nd Floor C-Wing
|
|
ENTRANCE CLOSURE: The direct route from the Merit Building to the County-City Building will close permanently Friday, Sept. 14 when the breezeway between South 9th Street and the loading dock entrance is shut down for the CCB Phase 2 renovation project. The two entrances to the north wing (C-Wing) from the breezeway also will be closed permanently.
Phase 2 is aimed at converting space on the 2nd floor of C-Wing into three courtrooms and adminstrative space for Superior Court and installing enhanced courthouse security systems. A new entry will be provided at the north end of C-wing as part of the $8.9 million Phase 2 work. |
| The interior stairwell at the north end of C-Wing will be temporarily closed on and off the 2nd Floor. The north stairwell will serve as an emergency exit to the first-floor and Tacoma Avenue for the duration of the project. |
 Click on map to enlarge. |
Back to Top
|
| Meeting Date |
Minutes/Handouts |
| Wednesday, August 8, 2007 |
Minutes |
| Tuesday, September 11, 2007 |
Minutes |
| Tuesday, September 25, 2007 |
Minutes |
| Tuesday, October 2, 2007 |
Minutes |
| Tuesday, October 9, 2007 |
Minutes |
| Tuesday, October 16, 2007 |
Minutes |
| Tuesday, October 23, 2007 |
Minutes |
| Tuesday, November 6, 2007 |
Minutes |
| Tuesday, November 13, 2007 |
Minutes |
| Tuesday, December 4, 2007 |
Minutes |
| Tuesday, December 11, 2007 |
Minutes |
| Tuesday, January 8, 2008 |
Minutes |
| Tuesday, January 15, 2008 |
Minutes |
| Tuesday, January 22, 2008 |
Minutes |
|
|
|
|
|
|
|
|
|
|
|
|
| |
 |
|
 |
8-24-07 Predemolition
9-11-07 Demolition
9-19-07 Demolition
09-20-07 Demolition
09-28-07 Demolition
September 2007. Demolition & Abatement of 2nd Floor C-Wing of County-City Building. |
10-15-07 Demolition
10-17-07 Demolition
10-18-07 Demolition
October 2007. Topping slab demolition & install 1st floor plumbing and electrical above ceiling |
11-01-07 Demolition
11-19-07 Demolition
November 2007. Install concrete slabs & waterproofing and install exterior walkway steel support |
12-04-07 Construction
12-20-07 Construction
December 2007. Demolish walls & ceiling in existing jail sallyport and construct temporary security walls. Install new exterior windows & spandrel panels, ductwork, and frame new walls & security door frames. |
 01-3-08 Construction
 01-15-08 Construction
January 2008. Install plumbing, electrical, and security electronics rough-in. Complete installation of exterior walkway at North wall. |
 Construction
February 2008. Install concrete ramp and walls at existing jail sallyport. Install electrical wiring and drywall at framed walls. |
 Construction
March 2008. Finish, texture drywall, and paint walls. Complete railing installation at ramp in ijail sallyport. |
 Construction
April 2008. Install ceiling, courtroom wood paneling, and casework. Install resilient flooring, light fixtures, and plumbing fixtures. |
 May 2008. Install fire sprinkler heads, detention fixtures, and electrical devices. Install window treatment, carpet flooring, and doors & hardware. |
 June 2008. Install decorative metal ceilings, final electrical devices, controls, toilet accessories |
 July 2008. Install courtroom pews, test fire alarm & security systems and final inspection |
 August 2008. Final Completion
|
|
|
|
|
|
|
| |
|
|
|