Word on the Street: Improvements to Wollochet Drive NW (East Bay Drive NW to Fillmore Drive NW)

What's Happening
Pierce County will be improving approximately 0.41 mile of Wollochet Drive NW (CRP 5542). Improvements, designed to relieve traffic congestion, include:

  • Expanding the roadway to five lanes.
  • Adding concrete curbs, gutters, sidewalks, and retaining walls.
  • Installing street lighting.
  • Adding an enclosed storm drain system.
  • Improving the existing traffic signal at Fillmore Drive NW.

Design work on this project is being coordinated with the Wollochet Drive NW (40th Street NW to East Bay Drive NW) (CRP 5696) project.

November 2011
This project was selected by the Transportation Improvement Board for $2.15M in Fiscal Year 2013 Rapid Action Funding. This funding fills a critical funding gap and will allow the project to be constructed starting in mid 2012.


Roadway Section


January 2012

  • Engineering: Final engineering design and permitting of the roadway, traffic signal system, roadway striping, and the storm drain system is nearing completion. Construction plans and specifications are nearly complete, as is coordination with private utilities for the relocation of their existing facilities.
  • Land: All of the needed right-of-way for the project has been acquired.


  • January 2008 to December 2009: Final engineering, utility relocation coordination, environmental documents, construction plans and estimates completed to 95% level. Project was 'shelved' pending funding for construction.
  • August 2011: Funding application was submitted for TIB Rapid Action selection.
  • November 2011: Project was selected by TIB for Rapid Action Funding.
  • February 2012: Project to be advertised for construction bids.
  • Spring 2012 - Fall 2013: Planned construction and private utility relocations.


Vicinity Map

(Click to Enlarge)

Roadway Picture

(Click to Enlarge)


How does the money get spent?

  • Engineering: $880,000
  • Right-of-Way Acquisition: $585,000
  • Construction: $4.70 million

Where does the money come from?

  • Transportation Improvement Board: $2,150,000
  • Traffic Impact Fees: $565,000
  • REET/Road Fund: $2,551,000
  • Developer: $62,000
  • Bond Funds: $837,000


Pat Baughman

Patrick Baughman, P.E., PMP
Engineering Resources Supervisor

More Details
Find more details such as revenues, cash flow and fact sheets.



Contact - Engineering Resources Supervisor
Email: Patrick Baughman, P.E., PMP
Phone: (253) 798-3157



Pierce County Public Works and Utilities
4301 South Pine Street, Suite 446
Tacoma, WA 98409-7207


CRP 5542 | January 2012