click to enlarge
Alignment
(see map below) The project begins on Brookdale Rd. E at Golden Given Rd. E, where an existing 72-inch interceptor pipe currently ends. This project will extend the 72-inch pipe west along Brookdale Rd. to its intersection with 8th Ave. E.
The new pipe will follow Brookdale Rd. E to where it merges with 131st St. E. and continue west to A St. S, where the new pipe will end. To connect to the rest of the sanitary sewer network, a new 36-inch diameter pipe will be installed along A St. S and connect to the existing pipe at 133rd St. E.
The existing pipe along 133rd St. E between 8th Ave. E and A St. will not be affected by the project.
Current Status
The project is in the final engineering phase. An alternative for the sewer pipe alignment has been developed. County survey crews may periodically be in the area to gather data needed to design the project.