1360-100 Lower Puyallup River Levee Repair Project
Click on picture to enlarge
1360-100 Lower Puyallup River Levee Repair Project

Project Manager
Al Zehni, PE
(253) 798-4677

Design Engineer
Jeffery Davidson
(253) 798-3090

Fish Biologist
Tom Nelson
(253) 798-4645

Design Consultant
URS / Entrix

Important Warning Information (pdf)

News Release for July 20, 2009 (pdf)

Overview

This project provides for repair to the existing Lower Puyallup River Levee by protecting about 200 linear feet of eroding bank on the right bank of the Puyallup River at river mile 5.2 in the City of Fife. This work will include constructing a matrix of precast concrete dolosse, logs, slash, planting, and other work.

A combination of logs and concrete eight foot dolosse will be used and placed along the bank line to anchor the logs and provide bank protection. The dolosse are designed to 'self settle', so in-water excavation is not necessary and the roughness of the structure will encourage silt deposition that will rebuild the bank. Eventually most of the dolosse and logs will be covered in sediment and match the appearance of the surrounding bank line. The logs will protrude slightly and provide fish cover. Native vegetation will also be planted at the site to increase the banks structural integrity and other environmental benefits.

Project Map

Conceptual Rendering
Note: rendering is directly after construction. Settlement and silt deposits are expected to completely cover the dolosse after the first high water.

What is a Dolos?

A dolos (plural dolosse) is an unusually-shaped large interlocking block of concrete, weighing up to 20 tons, used for protection of seawalls and to preserve shore earthworks from erosion.

The dolosse for this project weigh approximately 8 tons and measure about 8.5' by 8.5'.

Dolosse Front View

Dolosse Side View

Project Timeline (dates are approximate)
  • Final plans: April 2009
  • Bid opening: May 2009
  • Construction: Substantially Complete August 2009
  • Planting: Spring 2010

Estimated Project Cost: Under $500,000

  • Contractor awarded the dolosse fabrication is Bellingham Marine Industries, Inc. with a low bid of $171,360.
  • Contractor awarded the construction is Richard Phillips Marine, Inc. with a low bid of $207,322.

Contact Information:

If you have any questions, comments, or want to be kept informed about this project, please contact:

Project Manager
Al Zehni, PE
(253) 798-4677



Facebook
Fan us on Facebook


Twitter
Follow us on Twitter


Youtube
Watch us on Youtube



Privacy Policy | Text Only Version | Webmaster

Copyright ©1996-2011 Pierce County Washington. All rights reserved. Last Modified Jul 14 2010 2:46PM.