Canyon Road East - 99th Street Court East to 84th Street East (CRP 5726)

What’s Happening

Construction on a project to enhance safety and relieve traffic congestion on Canyon Road East between 99th Street Court East and 84th Street East began April 8. 


The project went into winter suspension on Jan. 11. Minor work will continue in the project area during the winter suspension. Any traffic impacts are expected to be minimal. We will post an update once regular construction work resumes. 


A significant portion of the construction work is expected to be completed by February 2021. Minor work will continue through February 2022. This schedule could be impacted by the winter suspension.

CRP_5726_Canyon_utility_work
Image of the project vicinity map.
Photo of Canyon Road East near the 96th Street East intersection.

About the Project


Canyon Road East from 96th Street East to 84th Street East will be widened to five lanes, with two through lanes in each direction and a two-way left-turn lane. This section will have paved shoulders, curbs, gutters, and sidewalks.  

Canyon Road East from 99th Street Court East to 96th Street East will be widened to four lanes, with two through lanes in each direction. This section will have paved shoulders and barrier curbs on the west side, and curbs, gutters, and sidewalks on the east side. 

A new traffic signal will be added at the Canyon Road East and 96th Street East intersection. The Canyon Road East and 84th Street East intersection will be widened, and a reconstructed traffic signal system was activated to accommodate the future configuration. 

Street lighting, an enclosed storm drain system, and stormwater storage and treatment facilities will be added as part of the project. 
Image of the proposed roadway section.

Construction Schedule

Utility relocation work began in 2019 and was completed in June.


East side of project
Construction work began on the east side of the project, with crews clearing the project site through mid-May. Work to install storm drainage facilities ran from mid-May to late August. A 35-foot-long retaining wall has been built about 200 feet east of the Canyon Road East and 84th Street East intersection.


Crews installed traffic signal system infrastructure from late July to late October. Curbs and gutters were installed from early September to early October. Paving work took place in early October. Work to install curb ramps started in November and was completed in December. Work to install sidewalks started in November, with minimal work possible during winter suspension. Work to install street lights began in December, with minimal work possible during winter suspension.

West side of project
Work shifted to the west side of the project in mid-October. Crews installed drainage facilities, street lights, traffic signal system infrastructure, curbs, gutters and sidewalks through the end of 2020. Additional work on street lights and traffic signal system infrastructure is possible during winter suspension.

A reconstructed traffic signal system at the Canyon Road East and 84th Street East intersection was activated on Dec. 9. The new traffic signal system at the Canyon Road East and 96th Street East intersection is expected to be activated in 2021.

Some paving work took place in December. The work is expected to resume in the spring. 
The road will be restriped into the new configuration once paving is complete. Paving work is weather dependent. 

Landscaping maintenance is expected to run through February 2022.

Rhino Construction is the contractor, and will follow updated safety guidelines that comply with current Centers for Disease Control and Prevention guidelines. The construction cost is approximately $8.9 million and is funded with County Road Funds, Traffic Impact Fees and Washington State Transportation Improvement Board Urban Arterial Program funds.

This project will support the planned Canyon Road Regional Connection Project. Learn more at www.canyonroadconnection.org

Project Timeline

August 23, 2019: Bid Opening date


September 3, 2019: Pierce County awarded the contract to Rino Construction.


December 2019 to April 2020: Utility Relocation Phase


April 8, 2020:  Notice to Proceed


April 2020 to mid-2021: Construction underway (Winter suspension effective Jan. 11, 2021)


February 2022: Landscape maintenance period ends


Right-of-Way Plans

Image of Right-of-Way Plans cover sheet.

Construction Plans (Sheets 1-60)

Image of Construction Plans cover sheet.

Construction Plans (Sheets 61-122)

Image of Construction Plans cover sheet.
Contact Us
Send a message arrow
Andrew Davis, P.E.
Construction Engineering Supervisor
Phone: (253) 798-6913
Address:
2702 S 42nd Street, Suite 109
Tacoma, WA 98409
Rino Construction
Contractor
Phone: (360) 469-4941
Address:
17937 Cedar Grove Road SE
Maple Valley, WA 98038