78th Avenue East / 184th Street East (CRP 5661)

78th Ave E / 184th St E Banner

What's Happening

Pierce County issued the Notice to Proceed on June 12, 2017.  The Contractor, Active Construction, Inc., has completed all the road and sidewalk work.  The project was suspended late Fall 2017 due to delays by the signal pole supplier. All work with the exception of minor electrical corrections to be completed April 2018.

About

 the Project


Planned improvements to the intersection of 78th Avenue East / 184th Street East (CRP 5661) are intended to increase the efficiency of the intersection and improve safety. Improvements would include the following:
  • Added left-turn lanes to 78th Avenue East.
  • Added concrete curb, gutter and sidewalk.
  • Added an enclosed storm drainage system, stormwater treatment and storage facilities.
  • Added a new traffic signal system and illumination at the intersection.
  • Added sidewalk on the south side of 184th Street East.

Project Timeline


March 03, 2017: Bid Opening

March 17, 2017:
Pierce County awarded the contract to 
Active Construction, Inc.  

May 23, 2017:
Pierce County hosted the Pre-Construction Meeting

June 12, 2017:
 Pierce County issued the Notice to Proceed

February 2018:
 Substantial Completion
 
April 2018:
 Physical Completion
Contact Us
Send a message arrow
Henry Gertje, P.E.
Construction Supervisor
Phone: (253) 798-6826
Active Construction, Inc.
Contractor
Phone: (253) 248-1091
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
5110 River Rd E
Tacoma, WA 98443