Pt Fosdick Dr NW / Stone Dr NW / 34th Ave NW (CRP 5581)

Pt Fosdick Dr NW/Stone Dr NW/34 St NW Banner

What’s Happening 


Construction on a roundabout at the intersection of Point Fosdick Drive Northwest, Stone Drive Northwest, and
34th Avenue Northwest began April 30. The bulk of the work is expected to be complete by early December.

30-day road closure
A segment of Stone Drive Northwest will be closed for approximately 30 days starting May 29 as part of construction on a roundabout at the intersection of Point Fosdick Drive Northwest, Stone Drive Northwest, and 34th Avenue Northwest.

Approximately 900 feet of Stone Drive Northwest will be closed from where it intersects with Point Fosdick Drive Northwest. The closure could extend beyond 30 days due to weather impacts or schedule changes.

During the closure, crews will excavate the road and build a new roadway surface that is up to 8 feet lower than the current road. 

A detour route of approximately 3.4 miles will take motorists from Stone Drive Northwest to Jahn Avenue Northwest to 32nd Street Northwest to 22nd Avenue Northwest to 36th Street Northwest to Point Fosdick Drive Northwest. 

detour_map_text

About the Project 


A roundabout is a circular intersection where motorists travel counterclockwise around a center island. 
This will be the first roundabout in unincorporated Pierce County built by the county.

The roundabout will be one lane, and will feature crosswalks with flashing lights that alert motorists that a 
pedestrian is crossing. The roundabout will include an apron that trucks can drive onto if extra room is needed 
when turning. 

The project will also include additional street lighting, pervious concrete sidewalks that reduce surface water runoff, 
curbs and gutters, and storm drainage treatment facilities. 

Traffic impacts


Throughout May, crews began clearing bushes and trees, installing storm drainage structures, and building a temporary bypass road on the east side of Point Fosdick Drive Northwest.

Following the closure, traffic will be shifted onto the temporary bypass road while crews regrade and build the legs of the intersection on Point Fosdick Drive Northwest and 34th Avenue Northwest. Crews will also build the roundabout’s island and the other project features. This work is expected to be complete by early December.


Motorists should expect each leg of the intersection to be reduced to one lane with alternating traffic in the project area
between 8 a.m. and 4 p.m. on weekdays throughout this work. Flaggers will be onsite to direct traffic during these hours. 


Crews will place a final layer of asphalt and apply final traffic markings in Spring 2019.

Miles Resources is the contractor. The construction cost is approximately $2.7 million. It is funded with a grant of
approximately $1.7 million from the Washington State Transportation Improvement Board’s Urban Arterial Program,
along approximately $1 million in County Road Funds.  

Pierce County held an open house in June 2015 to share information about the project and gather feedback on the design. 

Project Timeline

January 26, 2018: Bid Opening date

February 7, 2018: Pierce County awarded the contract to Miles Resources LLC

April 17, 2018: Pierce County hosted the Pre-Construction Meeting

April 30, 2018: Anticipated Notice to Proceed

December 2018: Anticipated Substantial Completion 

November 2018-November 2019: Planting establishment

December 2019:
 Anticipated Physical Completion
Contact Us
Send a message arrow
Henry Gertje, P.E.
Construction Supervisor
Phone: (253) 798-6826
Miles Resources, LLC
Contractor
Phone: (253) 383-3585
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
400 Valley Ave NE 
Puyallup, WA 98372