Canyon Road East - 192nd Street East to Frederickson Industrial Park Road East (CRP 5666)

Road with vehicles driving on it

What’s happening 


A Pierce County project to improve Canyon Road East between 192nd Street East and Frederickson Industrial Park Road East began April 25. The bulk of the work is expected to be completed by the fall.

Major construction work has been suspended until Sept. 26 while we wait for traffic signal poles to come in for the new signal at Canyon Road East and 184th Street East. The contractor may be onsite working on erosion control, street lighting, or other tasks. Motorists will see minor traffic impacts during this time. 

Final striping of the roadway is expected to take place in mid-August. 

About the project


Crews have:
  • Widened the road to accommodate a new two-way left turn lane. 
  • Added concrete curbs and gutters.
  • Added a combination of concrete and porous sidewalks.
  • Resurfaced the road from 192nd Street East to 187th Street East.
  • Added storm drainage facilities.

Upcoming work


Crews will:
  • Install street lighting.
  • Activate a new signal system at the Canyon Road East and 184th Street East intersection. This is expected in late 2018. 

Traffic impacts 


Motorists should expect minor traffic impacts on weekdays throughout the project. Motorists may want to consider taking 192nd Street East to 38th Avenue East to 176th Street East throughout the project to avoid the work area.

Both southbound lanes will be open on weekdays between 4:30 a.m. and 8:30 p.m. Lane restrictions may be in place outside of these hours.

Both northbound lanes will be open 5 a.m. to 8:30 a.m. on weekdays to support the morning commute. Northbound traffic may be reduced to one lane outside of these hours.

Nighttime work may be needed throughout the project. Alternating one-way traffic may be needed on 184th Street East, 187th Street East and 189th Street East during working hours.

Miles Resources is the contractor. The construction cost is approximately $2.5 million. It is funded with County Road Funds.  

Project timeline 


March 9, 2018: Bid Opening date 

March 20, 2018: Pierce County awarded the contract to Miles Resources LLC

April 11, 2018: Pierce County hosted the Pre-Construction Meeting

April 25, 2018: Pierce County issued Notice to Proceed 
 
November 2018: Anticipated Substantial Completion

December 2018: Anticipated Physical Completion

Contact Us
Send a message arrow
Curt Bright
Construction Inspection Supervisor
Phone: (253) 798-6824
Miles Resources, LLC
Contractor
Phone: (253) 383-3585
Address:
4301 South Pine Street, Suite 628
Tacoma, WA 98409
Address:
400 Valley Ave NE 
Puyallup, WA 98372