Construction Schedule
Crews removed vegetation and debris from the project area July 13.
From mid-July to mid-August, crews installed the enclosed storm drainage system. Crews installed the curbs, gutters, and sidewalks from mid-August to mid-September.
Crews paved the roadway the week of Sept. 28. Through mid-October, crews cleaned up the site, added landscaping, and striped the road and bike lanes.
The street lights, the flashing beacon and crosswalk will be installed starting Jan. 11.
The project’s contractor is Axum General Construction Inc. The construction cost is approximately $821,000. This project is funded with federal Surface Transportation Program (Urban) funds and County Road Funds.