121st Street South (C St S to SR7) (CRP 5878)

What’s happening

Bike lanes and sidewalks will be added to 121st Street South from C Street South to State Route 7 during a project that started July 13. 


A significant portion of the work was completed in mid-October. Remaining work will resume in January 2021 once additional materials are procured.


The project area is located near Pacific Lutheran University in Parkland. 


Work hours will be 7 a.m. to 3:30 p.m. The road may be reduced to one lane with alternating traffic during work hours. Access for pedestrians and bicyclists will be maintained.


Image of the project vicinity map.
Image of the project.

About the Project

The road shoulders will be widened to accommodate paved bike lanes, curbs, gutters, sidewalks and landscaping.


A marked crosswalk with a pedestrian-activated flashing beacon will be added approximately 50 feet west of the Pierce Transit transfer station. 


Street lights will also be added, along with an enclosed storm drainage system and stormwater treatment facilities.


Image of the project roadway section.
Image of project Right-of-Way Plans cover sheet.

Construction Schedule

Crews removed vegetation and debris from the project area July 13.


From mid-July to mid-August, crews installed the enclosed storm drainage system. Crews installed the curbs, gutters, and sidewalks from mid-August to mid-September. 


Crews paved the roadway the week of Sept. 28. Through mid-October, crews cleaned up the site, added landscaping, and striped the road and bike lanes. 


The street lights, the flashing beacon and crosswalk will be installed in January 2021 once additional materials are procured. 


The project’s contractor is Axum General Construction Inc. The construction cost is approximately $821,000. This project is funded with federal Surface Transportation Program (Urban) funds and County Road Funds.


Project Timeline

May 15, 2020: Bid Opening date


June 2, 2020: Pierce County awarded the contract to Axum General Construction Inc.


June 4, 2020: Pierce County hosted the Pre-Construction Meeting


July 13, 2020:  Notice to Proceed


January 2021: Construction expected to be complete

Contact Us
Send a message arrow
Andrew Davis, P.E.
Construction Supervisor
Phone: (253) 798-6913
Address:
2702 S 42nd St., Suite 109
Tacoma, WA 98409