Foothills Trail - Realignment at High Cedars Entrance

What's happening

Work on the realignment of Foothills Trail by High Cedars entrance will begin July 8, 2019.

The crews will be removing about 350 feet of existing asphalt trail, remove grass and shrubs, and excavate for the new alignment.

All trail traffic will experience delays during construction hours – 7:00 a.m. to 4:00 p.m.

The trail may be closed to all traffic during the construction work for public safety.

For more information about the trail please Click Here.


Work hours and traffic impacts

Work hours will run from 7:00 a.m. to 4:00 p.m. Monday to Friday. The path will be closed on July 8, 2019.

Project Timeline

March 22, 2019: Bid Opening date

March 29, 2019: Pierce County awarded the contract to KBH Construction

June 20, 2019: Pierce County hosted the Pre-Construction Meeting

July 8, 2019: Notice to Proceed

July 26, 2019: Anticipated Substantial and Physical Completion.

Contact Us


Andrew Davis, P.E.
Construction Engineering Supervisor
Phone: (253) 798-6913

Address:
2702 South 42nd Street, Suite 109
Tacoma, WA 98409

KBH Construction
Contractor
(360) 413-7888

Address:
4805 101st Lane SW
Olympia, WA 98512