Engineering: Pierce County has completed a field survey and is in the preliminary design stage.
Land: Right-of-Way needs will be evaluated.
Environmental: Necessary environmental permits will be obtained.
About the Project
Planned improvements to Cramer Road Northwest at its crossing with Glencove (CRP 5871) are intended to improve safety and replace the existing bridge, including the following:
Remove the existing bridge.
Reconstruct a new bridge and approach roadways.
The new bridge will be two lanes with paved shoulders and constructed with pre-tensioned precast concrete girders.
Cramer Road Northwest will be closed during construction.
Project Timeline
Fall 2018 to Winter 2020: Surveying, preliminary engineering and right-of-way plans.
Winter 2020 to Spring 2023: Right-of-way acquisition, environmental documentation, construction plans, specifications and estimates.