Gem Heights Drive East - ADA (Americans With Disabilities) Improvements 2020 (CRP 5904)

What's Happening


Engineering: 
We're beginning the preliminary engineering for the project. We'll be completing the field survey of the existing and proposed curb ramps and sidewalk locations.

About the Project


Planned improvements to Gem Heights Drive East - ADA (Americans With Disabilities) Improvements 2020 project (CRP 5904) are intended to improve accessibility and sidewalk connectivity on Gem Heights Drive East between 176th Street East and 168th Street East, and include the following:
  • Removing and reconstructing existing curb ramps and sidewalks within the project area that do not meet ADA requirements.
  • Adding new curb ramps and sidewalks within the project area where none exist.

Project Timeline

May 2019 to July 2019Complete field surveys. 

July 2019 to December 2019: Complete engineering and environmental documentation.

January 2020 to March 2020: 
Complete construction plans, specifications, and estimates.

Summer 2020: Construct improvements.
Contact Us
Send a message arrow
Patrick Baughman, P.E., PMP
Design Supervisor
Phone: (253) 798-3157
Address:
2702 S 42nd St., Suite 109
Tacoma, WA 98409