Schedule

banner image of 176th St E
Tentative improvement schedule

We will need many years to bring all facilities into compliance due to available resources.

We have developed a tentative schedule using overall cost data.

An average facility unit cost was identified to help create a tentative schedule:

  • Accessible Pedestrian Signal (APS) = $4,463 each 
  • Curb Ramp = $6,070 each
  • Driveway = $4,889 each 
  • Sidewalk = $105 per linear foot

With approximately $1,135,000 available each year for ADA improvement projects, we estimated the amount of design and construction work that is possible each year. We aim to design or construct the following each year:
APS
16–64
graphic of an accessible pedestrian signal
Curb Ramps
40–60
graphic of a curb ramp
Driveways
15–30
graphic of a driveway
Sidewalks (linear feet)
500–2,500
graphic of a sidewalk
From there, we developed the following table showing what could be completed in five-year periods:
  
Year Range Curb Ramps (ea.) APS (ea.) Driveways (ea.) Sidewalks (LF) Anticipated Program Funding
2020–2024 200–300 80–320 75–150 2,500–12,500 $ 5,675,000
2025–2029 200–300 80–261 75–150 2,500–12,500 $ 5,675,000
2030–2034 200–325 0–80 75–150 2,500–12,500 $ 5,675,000
2035–2039 200–325 0–80 75–150 2,500–12,500 $ 5,675,000
2040–2044 200–325 0–80 75–150 2,500–12,500 $ 5,675,000
2045+ 3,000–3,500 0–200 650–1,100 550,000–600,000 $ 67,674,723

Please keep in mind the amount of facilities improved or constructed may vary year-to-year due to factors such as selected project areas, available funding, and leadership priorities.