2nd Floor Restrooms
Restroom improvements include:
- Updating plumbing, fixtures and finishes
- Adding a single ADA restroom
- Adding a single lactation room
*Preliminary Construction Schedule
Demolition
• Phase I (North Restrooms) – 10/14/2019 to 10/25/2019
• Phase II (Single Restrooms) -11/25/2019 to 11/29/2019
Interior Framing & Rough-In of Electrical, Mechanical and Plumbing
• Phase I (North Restrooms)– 10/25/2019 to 11/15/2019
• Phase II (Single Restrooms) – 11/30/2019 to 12/06/2019
Finishes, Doors, Hardware, Trim & Misc. Specialties
• Phase I (North Restrooms)– 11/15/2019 to 11/22/2019
• Phase II– 12/07/2019 to 12/13/2019
Final Inspections, Furniture, & Occupancy
• Phase I (North Restrooms) – 11/23/2019 to 11/24/2019
• Phase II (Single Restrooms)– 12/14/2019 to 12/15/2019
*A tentative schedule will be finalized soon and updated regularly during the project.