Markham Avenue Northeast Retaining Wall Repairs (CRP 5839)

What’s Happening

Engineering: Pierce County has completed the project kick off meeting and is completing a field survey.


Land: Right-of-way needs will be evaluated.


Environmental: Necessary environmental permits will be obtained as needed.

Image of the project vicinity map.
Image of project photo.

About the Project

Planned improvements to Markham Avenue Northeast at approximately 1,250 feet W/O SR 509 (CRP 5839) are intended to repair or replace the failing retaining wall. Markham Avenue Northeast may have partial to full road closures during the project.

Project Timeline

Early 2020 to Fall 2021: Surveying, preliminary engineering and right-of-way plans.


Fall 2021 to Spring 2022: Right-of-way acquisition, environmental documentation, construction plans, specifications and estimates.


Summer 2022: Construction

Contact Us

Kraig Shaner, P.E.

Bridge Supervisor

Phone: (253) 798-2764

Address:

2702 S 42nd Street, Suite 109

Tacoma, WA 98409